Work in this order
This is the sequence followed in our small bathroom remodel guide. Skipping ahead is the classic mistake: choosing tile before the shower valve location is fixed can leave an awkward cut right at eye level.
01
Design and budget
Settle the layout, pick fixtures and get quotes. Order long-lead items like vanities and glass early. Bathroom Remodel Cost explains how to build the budget.
02
Permits
Moving plumbing, adding circuits or changing walls usually requires a permit. Your contractor or local building department can confirm.
03
Demolition
Remove fixtures, tile and drywall down to the studs where needed. This is when hidden rot, old wiring or leaks show up.
04
Rough-in
Plumbers and electricians move lines, install the shower valve, add blocking for grab bars or a wall-hung vanity, and run wiring for lights and the fan.
05
Inspection
If a permit was pulled, rough-in work is inspected before walls close.
06
Walls and waterproofing
Cement board or foam board goes up, then a waterproofing membrane in wet areas.
07
Tile
Floor and wall tile, grout, and sealing if the material needs it. Bathroom Tile Ideas covers sizes and patterns.
08
Fixtures and finish
Vanity, toilet, faucets, glass, lighting, mirror, paint and accessories.
Clearances to check before you draw
Most US jurisdictions follow the International Residential Code, sometimes with local amendments. Treat these numbers as minimums: a few extra inches in front of the toilet make a noticeable difference.
Toilet and sink
The centerline must be at least 15 inches from a side wall, partition or vanity, with at least 21 inches of clear floor space in front (IRC R307.1).
Shower
At least 900 square inches of interior area, no dimension under 30 inches, and an entry at least 22 inches wide (IRC P2708.1).
Shower glass
Glazing in or facing a shower or tub must be safety glazing (IRC R308.4.5).
What a remodel costs
Published figures differ because each source defines the project differently: a cosmetic update is not a full gut. Treat them as benchmarks, not quotes. Sources and details are in Bathroom Remodel Cost and Small Bathroom Remodel Cost.
| Source | Scope | Figure |
|---|---|---|
| This Old House (2026) | Average, bathrooms from 40 to 150 sq ft | $15,586 (most projects $6,456 to $24,715) |
| This Old House (2026) | Small, 40 to 60 sq ft | $12,695 to $14,845 |
| This Old House (2026) | Medium, 70 to 90 sq ft | $15,920 to $18,070 |
| This Old House (2026) | Large, 100 to 120 sq ft | $19,166 to $21,295 |
| This Old House (2026) | Primary suite, 130 sq ft and up | $22,370 to $24,715 |
| Cost vs. Value Report (2025) | Midrange remodel of a 5×7 bath | $26,138 national average |
| Fixr (February 2025) | 5×10 bathroom | $3,750 to $13,750, about $6,000 on average |
Where the money goes
Average cost of each component in the This Old House 2026 breakdown. Not every project includes every line.
| Line item | Average cost (2026) |
|---|---|
| Shower installation | $8,044 |
| Plumbing | $5,545 |
| Cabinetry | $2,929 |
| Insulation and drywall | $2,338 |
| Water heating upgrade | $1,478 |
| Tiling | $1,326 |
| Painting | $1,145 |
| Bathtub | $1,123 |
| Flooring | $1,114 |
| Toilet | $467 |
| Electrical | $456 |
| Bathtub faucets | $423 |
| Countertops | $332 |
A four-step estimate
No calculator needed for a realistic first number. Refine it with real quotes.
01
Measure the floor area
Multiply length by width. A 5×8 bathroom is 40 square feet.
02
Find your size band
Match the area to the size table above. A 40 sq ft bathroom falls in the small band, at $12,695 to $14,845.
03
Adjust for scope
A light refresh on the existing plumbing sits below the band, a standard remodel inside it, and a full gut with a custom shower or moved plumbing can approach the $26,138 Cost vs. Value benchmark.
04
Add a contingency
Set aside an extra 10 to 20 percent for surprises behind the walls. It is a budgeting rule of thumb, not a statistic.
What to keep and what to change
The logic of our budget remodel guide: leave the expensive-to-move parts alone and spend where you see and use the room.
Keep
The layout, a sound tub (reglazing changes its color without demolition), neutral tile that is not cracked or loose, and a solid vanity box that can be painted and fitted with new hardware.
Change
Paint made for humid rooms, the faucet and shower head in one matching finish, lighting at the mirror, hardware, and fresh caulk and grout.
Do not cut corners on
Waterproofing, a ventilation fan vented outside, electrical work near water (GFCI protection), and the shower valve: the IRC requires pressure-balance or thermostatic valves with a high-limit stop set to 120°F or lower.